Obtain water feasibility at the State or Municipality
(last modified: 19/07/2022)

This procedure allows to verify the feasibility of sufficient water supply at the state or municipality where the construction project is located.

This section of the portal is a compilation of the procedure possible requirements, since the information applicable to each municipality or state depends on particular legislation, the requirements for a specific location may vary from the compilation given here.

The required information is obtained at the office of the municipal or state agency that is responsible for the specific location. There you will be informed about the document to obtain, the requirements, costs, resolution time and applicable legislation for the municipality or state of your interest. Consult the directory of municipalities here.

Requirements

Possible requirements
1. Application in official format
Application in official format (Simple copy)

Request must be addressed to the municipal or state government or equivalent Agency.

2. Current official identification (IFE, INE, Passport or Professional License)
Current official identification (IFE, INE, Passport or Professional License) (Simple copy)

Owner's or legal representative identification.

3. Proof of ownership or possession of the property
Proof of ownership or possession of the property (Simple copy)

Proof of ownership or possession of the property before the Public Registry of Property (Deeds, Property Title or Attorney deed).

4. Articles of Incorporation
Articles of Incorporation (Simple copy)

In the case of a legal person, attach the Constitutive Act and document that accredits the legal representative.

5. Feasibility of use of land
Feasibility of use of land (original + Simple copy)
6. Alignment and official number
Alignment and official number (Simple copy)
7. Architectural Drawing
Architectural Drawing (Simple copy)
8. Hydraulic and sanitary plan
Hydraulic and sanitary plan (original + Simple copy)

Must specify the need for liters per second or m3 per month.